ByTenantsByTenants home

35-53 35 Avenue, Astoria, NY 11106

Built 1959 · 6-story elevator building · 579 apartments

Tenant reviews
None yetLived here? Reviews open soon.
Open violations
None openNo open housing violations on record.
Public record
Updated todayFrom the city’s own data (, 311, the courts), refreshed nightly.
What do these labels mean?
Tenant-reported
A resident's firsthand account of living here, moderated before it publishes, and labelled with whether we verified they lived there.
Official violation
A city inspector visited and recorded a code violation. HPD's own words, and its own hazard class.
Public complaint
A complaint somebody made to a city system, through HPD or 311. A report, not a finding: nobody has necessarily inspected it.
Public filing
A permit, a registration, a bedbug report: a document the owner filed with the city because the law requires it.
Court record
A Housing Court case HPD brought against the owner, or an eviction a city marshal carried out. A court's record: a case is an allegation until it ends in a finding.
Insufficient data
Not enough current information here to infer a pattern either way.

Tenant reviews

Tenant-reported

No tenant reviews yet. Lived here? Be the first.

Nothing above this section came from a tenant. It is all filed by the city, which means it only holds what somebody reported and an inspector wrote down, not what it is actually like to live here.

Not open yet. Reviews open when this neighbourhood does.

Heat season

No heat or hot-water complaints or violations were recorded here last winter (2025–26). That is the city's record: it only holds what somebody reported.

WinterDaysComplaintsViolations
2025–26000

The rules, 1 October to 31 May: from 6am to 10pm, when it is below 55°F outside, the apartment must be at least 68°F; overnight it must be at least 62°F whatever the weather. Hot water must be at least 120°F all year. A tenant without heat can report it to 311.

Rent stabilization

Public filing

This building is not on the state's list of buildings with rent-stabilized apartments for 2024. That is not proof none are: an owner who did not register is missing from the list too.

Source: Rent Guidelines Board building list, from the state's 2024 registrations. To know about one apartment, a tenant can ask the state for its rent history through Ask HCR.

City violations

Official violation

HPD has no violations on record for this building. That is the city’s record, not a verdict: a violation only exists if somebody complained and an inspector came.

Complaints to the city

Public complaint

Complaints are reports made to the city. They are not confirmed findings. They come from HPD and from 311, and the same problem can appear more than once if more than one neighbour called.

225 complaints in three years, 115 of them in the last twelve months.

  • Noise112 / 214
  • Heat and hot water0 / 4
  • Construction and illegal work2 / 3
  • Garbage and cleanliness1 / 2
  • Elevator0 / 1
  • Leaks and plumbing0 / 1

Last twelve months / last three years. The solid part of each bar is the last twelve months.

Court records

Court record

Housing Court cases

Cases the city’s housing department (HPD) brought against the owner, usually to force repairs or restore heat. A case is an allegation; where the court recorded an outcome, it is shown.

2 cases, all closed.

  • Tenant Action/Harassment

    Opened 19 Dec 2025No harassment found

  • Tenant Action

    Opened 5 Jun 2017

Evictions

Residential evictions carried out by a city marshal since 2017. Most follow a case for unpaid rent, so a count here is not by itself a finding about the building or the landlord. We show how many, never which apartment.

  • 20261 eviction
  • 20251 eviction
  • 20194 evictions
  • 20181 eviction
  • 20173 evictions

Filings

Public filing

Building permits

34 permits currently in force.

  • Solar

    Installation of 43.055 kw solar energy system on roof. No change of occupancy, use or egress

    Issued 4 Jun 2026Expires 26 Feb 2027

  • General Construction · Structural

    SITE YARD WORK AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY. Application to be reviewed with the Development HUB.

    Issued 24 Apr 2026Expires 31 Mar 2027

  • General Construction

    INSTALLATION OF NEW 8FT HIGH ALUMINUM FENCE AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY. Application to be reviewed with the Development HUB.

    Issued 22 Apr 2026Expires 31 Mar 2027

  • Structural

    NYCHA BOILER_removal of existing concrete entry stairs, installation of new concrete entry stairs and pads for mech. equipment, mounting of risers to exterior facade of the building

    Issued 20 Mar 2026Expires 3 Dec 2026

  • Mechanical Systems

    NYCHA BOILER_REPLACEMENT OF EXISTING VACUUM AND CONDENSATE PUMPS, INSTALLATION OF COMBUSTION AIR DUCTWORK AND FLUES FOR NEW DOMESTIC AND HOT WATER HEATERS.

    Issued 20 Mar 2026Expires 3 Dec 2026

  • Structural

    NYCHA BOILER_removal of existing concrete entry stairs, installation of new concrete entry stairs and pads for mech. equipment, mounting of risers to exterior facade of the building

    Issued 20 Mar 2026Expires 3 Dec 2026

  • Mechanical Systems

    REPLACEMENT OF EXISTING VACUUM AND CONDENSATE PUMPS, INSTALLATION OF COMBUSTION AIR DUCTWORK AND FLUES FOR NEW DOMESTIC AND HOT WATER HEATERS.

    Issued 19 Mar 2026Expires 3 Dec 2026

  • Mechanical Systems

    NYCHA BOILER_REPLACEMENT OF EXISTING VACUUM AND CONDENSATE PUMPS, INSTALLATION OF COMBUSTION AIR DUCTWORK AND FLUES FOR NEW DOMESTIC AND HOT WATER HEATERS.

    Issued 19 Mar 2026Expires 3 Dec 2026

  • Structural

    NYCHA BOILER_removal of existing concrete entry stairs, installation of new concrete entry stairs and pads for mech. equipment, mounting of risers to exterior facade of the building

    Issued 19 Mar 2026Expires 3 Dec 2026

  • General Construction

    Replacement of existing vacuum pumps, exhaust fan, sum pumps, piping. Replacement of existing hot water tanks and piping with gas-fired water heaters. New exterior side-wall flue to the roof. Installation of new gas piping.Replacement of doors and windows

    Issued 19 Mar 2026Expires 3 Dec 2026

  • Structural

    removal of existing concrete entry stairs, installation of new concrete entry stairs and pads for mech. equipment, mounting of risers to exterior facade of the building

    Issued 19 Mar 2026Expires 3 Dec 2026

  • General Construction

    Replacement of existing vacuum pumps, exhaust fan, sum pumps, piping. Replacement of existing hot water tanks and piping with gas-fired water heaters. New exterior side-wall flue to the roof. Installation of new gas piping.Replacement of doors and windows

    Issued 18 Mar 2026Expires 3 Dec 2026

  • Mechanical Systems

    NYCHA BOILER_REPLACEMENT OF EXISTING VACUUM AND CONDENSATE PUMPS, INSTALLATION OF COMBUSTION AIR DUCTWORK AND FLUES FOR NEW DOMESTIC AND HOT WATER HEATERS.

    Issued 18 Mar 2026Expires 3 Dec 2026

  • Structural

    NYCHA BOILER_removal of existing concrete entry stairs, installation of new concrete entry stairs and pads for mech. equipment, mounting of risers to exterior facade of the building

    Issued 18 Mar 2026Expires 3 Dec 2026

  • Mechanical Systems

    NYCHA BOILER_REPLACEMENT OF EXISTING VACUUM AND CONDENSATE PUMPS, INSTALLATION OF COMBUSTION AIR DUCTWORK AND FLUES FOR NEW DOMESTIC AND HOT WATER HEATERS.

    Issued 18 Mar 2026Expires 3 Dec 2026

  • Structural

    NYCHA BOILER_removal of existing concrete entry stairs, installation of new concrete entry stairs and pads for mech. equipment, mounting of risers to exterior facade of the building

    Issued 18 Mar 2026Expires 3 Dec 2026

  • General Construction

    Replacement of existing vacuum pumps, exhaust fan, sum pumps, piping. Replacement of existing hot water tanks and piping with gas-fired water heaters. New exterior side-wall flue to the roof. Installation of new gas piping.Replacement of doors and windows

    Issued 18 Mar 2026Expires 3 Dec 2026

  • Mechanical Systems

    NYCHA BOILER_REPLACEMENT OF EXISTING VACUUM AND CONDENSATE PUMPS, INSTALLATION OF COMBUSTION AIR DUCTWORK AND FLUES FOR NEW DOMESTIC AND HOT WATER HEATERS.

    Issued 18 Mar 2026Expires 3 Dec 2026

  • Structural

    NYCHA BOILER_removal of existing concrete entry stairs, installation of new concrete entry stairs and pads for mech. equipment, mounting of risers to exterior facade of the building

    Issued 18 Mar 2026Expires 3 Dec 2026

  • General Construction

    Replacement of existing vacuum pumps, exhaust fan, sum pumps, piping. Replacement of existing hot water tanks and piping with gas-fired water heaters. New exterior side-wall flue to the roof. Installation of new gas piping.Replacement of doors and windows

    Issued 18 Mar 2026Expires 3 Dec 2026

  • Mechanical Systems

    NYCHA BOILER_REPLACEMENT OF EXISTING VACUUM AND CONDENSATE PUMPS, INSTALLATION OF COMBUSTION AIR DUCTWORK AND FLUES FOR NEW DOMESTIC AND HOT WATER HEATERS.

    Issued 18 Mar 2026Expires 3 Dec 2026

  • General Construction

    Replacement of existing vacuum pumps, exhaust fan, sum pumps, piping. Replacement of existing hot water tanks and piping with gas-fired water heaters. New exterior side-wall flue to the roof. Installation of new gas piping.Replacement of doors and windows

    Issued 18 Mar 2026Expires 3 Dec 2026

  • Mechanical Systems

    REPLACEMENT OF EXISTING VACUUM AND CONDENSATE PUMPS, INSTALLATION OF COMBUSTION AIR DUCTWORK AND FLUES FOR NEW DOMESTIC AND HOT WATER HEATERS.

    Issued 18 Mar 2026Expires 3 Dec 2026

  • Structural

    removal of existing concrete entry stairs, installation of new concrete entry stairs and pads for mech. equipment, mounting of risers to exterior facade of the building

    Issued 18 Mar 2026Expires 3 Dec 2026

  • Foundation · General Construction · Structural

    Removal of existing concrete entry stairs, installation of new concrete entry stairs, and pads for mechanical equipment, mounting of risers to exterior facade of the building.

    Issued 18 Mar 2026Expires 3 Dec 2026

  • Solar

    Installation of 39.785 kw solar energy system on roof. No change occupancy, use or egress

    Issued 4 Mar 2026Expires 26 Feb 2027

  • Solar

    Installation of 78.48 kw solar energy system on roof. No change of occupancy, use or egress

    Issued 4 Mar 2026Expires 26 Feb 2027

  • Solar

    Installation of 39.785 kw solar energy system on roof. No change of occupancy, use or egress.

    Issued 4 Mar 2026Expires 26 Feb 2027

  • Solar

    Installation of 40.33 kw solar energy system on roof. No change of occupancy, use or egress

    Issued 3 Mar 2026Expires 26 Feb 2027

  • Solar

    Installation of 45.235 kw solar energy system on roof. No change of occupancy, use or egress

    Issued 3 Mar 2026Expires 26 Feb 2027

  • Solar

    Installation of 80.66 kw solar energy system on roof. No change occupancy, use or egress

    Issued 3 Mar 2026Expires 26 Feb 2027

  • Solar

    Installation of 39.785 kw solar energy system on roof. No change of occupancy, use or egress

    Issued 3 Mar 2026Expires 26 Feb 2027

  • Solar

    Installation of 79.025 kw solar energy system on roof. No change of occupancy, use or egress

    Issued 3 Mar 2026Expires 26 Feb 2027

  • Plumbing

    NYCHA BOILER_REMOVE AND REPLACE HOT WATER HEATERS AND WATER LINES, RECIRCULATION PUMPS, DRAINS . INSTALL NEW SUMP PUMPS AND DISCHARGE LINES. INSTALL NEW AIR INTAKES AND EXHAUST FOR WATER HEATERS.

    Issued 5 Nov 2025Expires 5 Nov 2026

Show 25 expired or finished
  • Plumbing

    NYCHA BOILER_REMOVE AND REPLACE HOT WATER HEATERS AND WATER LINES, RECIRCULATION PUMPS, DRAINS . INSTALL NEW SUMP PUMPS AND DISCHARGE LINES. INSTALL NEW AIR INTAKES AND EXHAUST FOR WATER HEATERS.

    Issued 6 Jan 2026Expired 31 Jan 2026

  • Plumbing

    REMOVE AND REPLACE OR PROVIDE NEW SUMP PUMPS AND DISCHARGE LINES.

    Issued 20 Nov 2025Expired 31 Jan 2026

  • Plumbing

    SUBSEQUENT FILING FOR PL WORK - STORM/DRAINAGE PIPING, DRAINS, DRYWELL RETENTION.

    Issued 24 Apr 2025Expired 31 Dec 2025

  • General Construction

    Infrastructure to improve management of stormwater runoff from the tributary impervious surfaces. On-site Green Infrastructure Cloudburst Pilot Project. DEP Capital Contract No. GQ-H-RAVE, Ravenswood Houses, NYCHA facility.

    Issued 8 Apr 2025Expired 1 Apr 2026

  • Construction Fence

    RAVENSWOOD HOUSES (BUILDING #9), INSTALLATION OF 8 FEET HIGH CONSTRUCTION FENCE IN CONJUNCTION WITH DOB # Q00455180 TO SECURE THE STAGING AREA. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.

    Issued 24 Mar 2025Expired 31 Dec 2025

  • Construction Fence

    RAVENSWOOD HOUSES (BUILDING #13), INSTALLATION OF 125 LINEAR FEET OF CONSTRUCTION FENCE IN CONJUNCTION WITH DOB # Q00455195 TO SECURE THE STAGING AREA. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.

    Issued 21 Mar 2025Expired 31 Dec 2025

  • Plumbing

    NYCHA BOILER_REMOVE AND REPLACE HOT WATER HEATERS AND WATER LINES, RECIRCULATION PUMPS, DRAINS . INSTALL NEW SUMP PUMPS AND DISCHARGE LINES. INSTALL NEW AIR INTAKES AND EXHAUST FOR WATER HEATERS.

    Issued 20 Mar 2025Expired 31 Jan 2026

  • Construction Fence

    RAVENSWOOD HOUSES (BUILDING #12), INSTALLATION OF 50 LINEAR FEET OF CONSTRUCTION FENCE IN CONJUNCTION WITH DOB # Q00944602 TO SECURE THE STAGING AREA. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.

    Issued 19 Mar 2025Expired 31 Dec 2025

  • Support of Excavation

    RAVENSWOOD HOUSES - BUILDING #13, INSTALLATION OF TEMPORARY SHORING AND SUPPORT FOR EXCAVATION IN CONJUNCTION WITH DOB # Q01010455. NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.

    Issued 18 Mar 2025Expired 31 Dec 2025

  • Support of Excavation

    RAVENSWOOD HOUSES - BUILDING #16, INSTALLATION OF TEMPORARY SHORING AND SUPPORT FOR EXCAVATION IN CONJUNCTION WITH DOB # Q01010458. NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.

    Issued 18 Mar 2025Expired 31 Dec 2025

  • Support of Excavation

    RAVENSWOOD HOUSES - BUILDING #9, INSTALLATION OF TEMPORARY SHORING AND SUPPORT FOR EXCAVATION IN CONJUNCTION WITH DOB # Q01010451. NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.

    Issued 18 Mar 2025Expired 31 Dec 2025

  • Construction Fence

    RAVENSWOOD HOUSES (BUILDING #10), INSTALLATION OF 50 LINEAR FEET OF CONSTRUCTION FENCE IN CONJUNCTION WITH DOB # Q00455185 TO SECURE THE STAGING AREA. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.

    Issued 18 Mar 2025Expired 31 Dec 2025

  • Construction Fence

    RAVENSWOOD HOUSES (BUILDING #11), INSTALLATION OF 50 LINEAR FEET OF CONSTRUCTION FENCE IN CONJUNCTION WITH DOB # Q00455189 TO SECURE THE STAGING AREA. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.

    Issued 18 Mar 2025Expired 31 Dec 2025

  • Construction Fence

    RAVENSWOOD HOUSES (BUILDING #14), INSTALLATION OF 100 LINEAR FEET OF CONSTRUCTION FENCE IN CONJUNCTION WITH DOB # Q00455204 TO SECURE THE STAGING AREA. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.

    Issued 18 Mar 2025Expired 31 Dec 2025

  • Construction Fence

    RAVENSWOOD HOUSES (BUILDING #15), INSTALLATION OF 100 LINEAR FEET OF CONSTRUCTION FENCE IN CONJUNCTION WITH DOB # Q00455213 TO SECURE THE STAGING AREA. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.

    Issued 18 Mar 2025Expired 31 Dec 2025

  • Construction Fence

    RAVENSWOOD HOUSES (BUILDING #16), INSTALLATION OF 100 LINEAR FEET OF CONSTRUCTION FENCE IN CONJUNCTION WITH DOB # Q00455218 TO SECURE THE STAGING AREA. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.

    Issued 18 Mar 2025Expired 31 Dec 2025

  • Support of Excavation

    RAVENSWOOD HOUSES - BUILDING #10, INSTALLATION OF TEMPORARY SHORING AND SUPPORT FOR EXCAVATION IN CONJUNCTION WITH DOB # Q00455185, Q01010452. NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.

    Issued 18 Mar 2025Expired 31 Dec 2025

  • Support of Excavation

    RAVENSWOOD HOUSES - BUILDING #14, INSTALLATION OF TEMPORARY SHORING AND SUPPORT FOR EXCAVATION IN CONJUNCTION WITH DOB # Q01010456. NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.

    Issued 18 Mar 2025Expired 31 Dec 2025

  • Support of Excavation

    RAVENSWOOD HOUSES - BUILDING #15, INSTALLATION OF TEMPORARY SHORING AND SUPPORT FOR EXCAVATION IN CONJUNCTION WITH DOB # Q01010457. NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.

    Issued 18 Mar 2025Expired 31 Dec 2025

  • Plumbing

    NYCHA BOILER_REMOVE AND REPLACE HOT WATER HEATERS AND WATER LINES, RECIRCULATION PUMPS, DRAINS . INSTALL NEW SUMP PUMPS AND DISCHARGE LINES. INSTALL NEW AIR INTAKES AND EXHAUST FOR WATER HEATERS.

    Issued 12 Mar 2025Expired 31 Jan 2026

  • Plumbing

    NYCHA BOILER_REMOVE AND REPLACE HOT WATER HEATERS AND WATER LINES, RECIRCULATION PUMPS, DRAINS . INSTALL NEW SUMP PUMPS AND DISCHARGE LINES. INSTALL NEW AIR INTAKES AND EXHAUST FOR WATER HEATERS.

    Issued 6 Feb 2025Expired 31 Jan 2026

  • Support of Excavation

    RAVENSWOOD HOUSES - BUILDING #11, INSTALLATION OF TEMPORARY SHORING AND SUPPORT FOR EXCAVATION IN CONJUNCTION WITH DOB # Q00455189, Q01010454. NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.

    Issued 8 Jan 2025Expired 15 Mar 2025

  • Support of Excavation

    RAVENSWOOD HOUSES - BUILDING #12, INSTALLATION OF TEMPORARY SHORING AND SUPPORT FOR EXCAVATION IN CONJUNCTION WITH DOB # Q01124359, Q00944602-S4. NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.

    Issued 21 Nov 2024Expired 1 Jan 2025

  • Plumbing

    REMOVE AND REPLACE HOT WATER HEATERS AND WATER LINES, RECIRCULATION PUMPS, DRAINS . INSTALL NEW SUMP PUMPS AND DISCHARGE LINES. INSTALL NEW AIR INTAKES AND EXHAUST FOR WATER HEATERS.

    Issued 8 Nov 2024Expired 8 Nov 2025

  • Plumbing

    Replacement of existing vacuum and condensate pumps. Installation of flues for new domestic and hot water heaters.

    Issued 20 Sept 2024Expired 20 Sept 2025

Annual bedbug report

Every multiple dwelling in New York must file this once a year. A report of zero infested units is good news. No report is not: failing to file is itself a violation.

No bedbug report on file for this building. That usually means the owner did not file one, not that there is nothing to report.

Ownership and management

Public filing

Associations come from registration records and may be incomplete. Owners register with HPD once a year, so a change of hands can go unrecorded for a full cycle.

No current HPD registration for this address. Buildings the owner occupies, and some small ones, are not required to register, but a rental building that should be registered and is not is itself a violation.

Wrong company, wrong date, or a change that is not reflected here? Report a correction.

What to ask at the viewing

Drawn from this building’s record above. They are questions, not conclusions: the point is to find out, in the twenty minutes you get inside, what the public record cannot tell you.

  1. 34 active construction permits on file. Ask what is being done, on which floors, and until when, and whether it affects heat, water or the elevator.
  2. The building's HPD registration is out of date or names nobody we could identify. Ask who the managing agent is and get a name, a phone number and an address in writing before you sign.
  3. Ask what the deposit is, exactly what can be deducted from it, and how and when it comes back.
  4. Ask who to call when something breaks, what happens after hours and at weekends, and how long a repair normally takes.

Ask for anything that matters in writing; an email after the viewing is enough. We are not your lawyer and this is not legal advice.

Questions about this building

BBL 4003350002 · Block 335, Lot 2 · Building class D1