1601 Dekalb Avenue, Brooklyn, NY 11237

Built 2024 · 9-story elevator building · 128 apartments

Tenant reviews
None yetLived here? Reviews open soon.
Open violations
None openNo open housing violations on record.
Public record
Updated todayFrom the city’s own data (, 311, the courts), refreshed nightly.
What do these labels mean?
Tenant-reported
A resident's firsthand account of living here, moderated before it publishes, and labelled with whether we verified they lived there.
Official violation
A city inspector visited and recorded a code violation. HPD's own words, and its own hazard class.
Public complaint
A complaint somebody made to a city system, through HPD or 311. A report, not a finding: nobody has necessarily inspected it.
Public filing
A permit, a registration, a bedbug report: a document the owner filed with the city because the law requires it.
Court record
A Housing Court case HPD brought against the owner, or an eviction a city marshal carried out. A court's record: a case is an allegation until it ends in a finding.
Insufficient data
Not enough current information here to infer a pattern either way.

Tenant reviews

Tenant-reported

No tenant reviews yet. Lived here? Be the first.

Nothing above this section came from a tenant. It is all filed by the city, which means it only holds what somebody reported and an inspector wrote down, not what it is actually like to live here.

Not open yet. Reviews open when this neighbourhood does.

Heat season

No heat or hot-water complaints or violations were recorded here last winter (2025–26). That is the city's record: it only holds what somebody reported.

WinterDaysComplaintsViolations
2025–26000

The rules, 1 October to 31 May: from 6am to 10pm, when it is below 55°F outside, the apartment must be at least 68°F; overnight it must be at least 62°F whatever the weather. Hot water must be at least 120°F all year. A tenant without heat can report it to 311.

Rent stabilization

Public filing

This building is not on the state's list of buildings with rent-stabilized apartments for 2024. That is not proof none are: an owner who did not register is missing from the list too.

Source: Rent Guidelines Board building list, from the state's 2024 registrations. To know about one apartment, a tenant can ask the state for its rent history through Ask HCR.

City violations

Official violation

HPD has no violations on record for this building. That is the city’s record, not a verdict: a violation only exists if somebody complained and an inspector came.

Complaints to the city

Public complaint

Complaints are reports made to the city. They are not confirmed findings. They come from HPD and from 311, and the same problem can appear more than once if more than one neighbour called.

17 complaints in three years, 3 of them in the last twelve months.

  • Noise3 / 13
  • Construction and illegal work0 / 3
  • Garbage and cleanliness0 / 1

Last twelve months / last three years. The solid part of each bar is the last twelve months.

Court records

Court record

Housing Court cases

Cases the city’s housing department (HPD) brought against the owner, usually to force repairs or restore heat. A case is an allegation; where the court recorded an outcome, it is shown.

No HPD Housing Court cases on record for this building.

Evictions

Residential evictions carried out by a city marshal since 2017. Most follow a case for unpaid rent, so a count here is not by itself a finding about the building or the landlord. We show how many, never which apartment.

No marshal evictions recorded at this building since 2017.

Filings

Public filing

Building permits

1 permit currently in force.

  • Foundation · New building

    Issued 10 Dec 2025Expires 31 Dec 2026

Show 14 expired or finished
  • Standpipe

    Install temporary dry standpipe system during construction as per plans filed. No change to use, egress or occupancy. Filed in conjunction with NB# 321594672

    Issued 23 Dec 2025Expired 6 Oct 2026

  • Sprinklers · Standpipe

    Install combined sprinkler/standpipe system as per plans filed. No change to use, egress, or occupancy. Filed in conjunction with NB# 321594672.

    Issued 11 Dec 2025Expired 6 Oct 2026

  • Supported Scaffold

    Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.

    Issued 28 Jul 2025Expired 13 May 2026

  • Protection and Mechanical Methods

    Installation of a temporary roof protection and overhead protection per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application

    Issued 10 Jun 2025Expired 13 May 2026

  • Protection and Mechanical Methods

    EQUIPMENT USE (DEKALB BLDG): SINGLE 7000# CAPACITY PERSONNEL/MATERIAL HOIST DURING NB CONST, FILED SEP. HOIST SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. ELEVATOR APPLICATION SUBMITTED SEPARATELY

    Issued 15 May 2025Expired 13 May 2026

  • Protection and Mechanical Methods

    EQUIPMENT USE (HART BLDG): SINGLE 7000# CAPACITY PERSONNEL/MATERIAL HOIST DURING NB CONST, FILED SEP. HOIST SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. ELEVATOR APPLICATION SUBMITTED SEPARATELY

    Issued 15 May 2025Expired 13 May 2026

  • Sidewalk Shed

    Installation of a temporarily heavy-duty sidewalk shed posts in the street per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.

    Issued 1 May 2025Expired 1 May 2026

  • Construction Fence

    Installation of a temporary construction fence per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.

    Issued 30 Apr 2025Expired 30 Apr 2026

  • Suspended Scaffold

    Suspended Scaffold Installation as per plans filed herewith. No change in use, egress or occupancy

    Issued 6 Mar 2025Expired 6 Mar 2026

  • Plumbing

    Plumbing work as per plans filed. No change to use, egress, or occupancy. Filed in conjunction with NB #321594672.

    Issued 30 Dec 2024Expired 30 Dec 2025

  • Structural

    Structural work as per plans filed. No change to use, egress, or occupancy. Filed in conjunction with NB #321594672.

    Issued 11 Dec 2024Expired 11 Dec 2025

  • Construction Fence

    Installation of Temporary Construction Fence in Sidewalk and on Roadway.

    Issued 11 Dec 2024Expired 11 Dec 2025

  • Mechanical Systems

    Mechanical work as per plans filed. No change to use, egress, or occupancy. Filed in conjunction with NB #321594672.

    Issued 25 Mar 2024Expired 25 Mar 2025

  • Construction Fence

    Install new temporary construction fence as per plans filed. No change to use, egress or occupancy. Filed in conjunction with NB #321594672.

    Issued 8 Feb 2024Expired 8 Feb 2025

Annual bedbug report

Every multiple dwelling in New York must file this once a year. A report of zero infested units is good news. No report is not: failing to file is itself a violation.

No bedbug report on file for this building. That usually means the owner did not file one, not that there is nothing to report.

Ownership and management

Public filing

Associations come from registration records and may be incomplete. Owners register with HPD once a year, so a change of hands can go unrecorded for a full cycle.

  • Registered managing agent

    RISEBORO COMMUNITY PARTNERSHIP

    Public records list RISEBORO COMMUNITY PARTNERSHIP as the registered managing agent for this address as of 23 Sept 2026. Source: HPD registration.

    Other buildings listed under this agent (58 in the records we hold, 10 shown)

    Show 7 more

    No combined rating for this agent yet. A portfolio rating needs at least 5 verified reviews across 2 or more buildings; currently 0.

  • Owner of record

    1601 DEKALB OWNER LLC

    Public records list 1601 DEKALB OWNER LLC as the owner of record for this address as of 23 Sept 2026. Source: HPD registration.

Wrong company, wrong date, or a change that is not reflected here? Report a correction.

What to ask at the viewing

Drawn from this building’s record above. They are questions, not conclusions: the point is to find out, in the twenty minutes you get inside, what the public record cannot tell you.

  1. 1 active construction permit on file. Ask what is being done, on which floors, and until when, and whether it affects heat, water or the elevator.
  2. Ask what the deposit is, exactly what can be deducted from it, and how and when it comes back.
  3. Ask who to call when something breaks, what happens after hours and at weekends, and how long a repair normally takes.

Ask for anything that matters in writing; an email after the viewing is enough. We are not your lawyer and this is not legal advice.

Questions about this building

BBL 3032370023 · Block 3237, Lot 23 · Building class D1